How many CarGo robots do you need: a calculation for warehouses and manufacturing
How to work out how many mobile robots a warehouse or production site needs from route length, loading time and the number of trips. With formulas and two examples.
CarGo 300 input data
Note: 5 hours is driving time. While the robot waits at loading or unloading it uses almost no charge, so real operating time on one charge is noticeably longer than 5 hours.
The formula
1. Round-trip time = 2 × route length (m) ÷ 48 m/min
2. Cycle = round-trip time + loading + unloading
3. Trips per hour per robot = 60 ÷ cycle
4. Trips per charge = 300 min of driving ÷ round-trip time
5. Robots needed = required trips per hour ÷ trips per hour per robot (round up)
Loading and unloading time depends on your process. In the examples below we assume 2 minutes for each operation — these are illustrative figures; during a pilot we measure the real ones.
Example 1. Manufacturing: storage → assembly line, 250 m
| Metric | Calculation | Result |
|---|---|---|
| Round trip | 500 m ÷ 48 m/min | ≈10.4 min |
| Cycle with loading and unloading | 10.4 + 2 + 2 | ≈14.4 min |
| Trips per hour per robot | 60 ÷ 14.4 | ≈4 |
| Trips per charge | 300 ÷ 10.4 | ≈28 (≈6.7 h of work) |
| Load per charge | 28 × up to 300 kg | up to ≈8.4 t |
If the line needs 10 deliveries per hour, you need 10 ÷ 4 ≈ 3 robots. One charge covers almost a full shift, and RMS schedules charging during line pauses.
Example 2. Warehouse: receiving → storage, 100 m
| Metric | Calculation | Result |
|---|---|---|
| Round trip | 200 m ÷ 48 m/min | ≈4.2 min |
| Cycle with loading and unloading | 4.2 + 2 + 2 | ≈8.2 min |
| Trips per hour per robot | 60 ÷ 8.2 | ≈7 |
| Trips per charge | 300 ÷ 4.2 | ≈71 (≈9.7 h of work) |
| Load per charge | 71 × up to 300 kg | up to ≈21 t |
On short routes the bottleneck is not the battery but loading speed. Here one charge lasts more than a shift, and productivity grows if loading is faster — for example, if totes are placed on the robot in advance.
What to consider in a real calculation
- People and turns. The robot slows down in narrow aisles and near people — 0.8 m/s is already the average route speed including this.
- Peaks. Calculate for the busiest hour of the shift, not the average.
- Reserve. For critical lines, plan +1 robot to cover charging and maintenance.
- Empty runs. If there is a load in both directions (parts to the line, empty totes back), the robot makes no empty trips and the economics improve.
How RMS helps
Counting robots is half the job. The other half is distributing tasks so that none stands idle or runs out of charge mid-shift. That is what the RMS robot management system is for:
- Tasks come from a staff member's phone, from WMS or MES.
- Allocation. The free robot is not always the best one: a robot finishing a trip nearby can be better. The RMS autopilot considers the approach, remaining work, priority, load weight and charge. At the start it works in suggestion mode: the system proposes and a person confirms.
- Charge. Monitoring shows each robot's charge, and charging is planned for pauses rather than mid-trip.
- Roads, not zones. Roads are drawn between points, so trip time is predictable and the calculation above matches practice.
- Reports. Trips, driving time and idle time per shift show whether you have enough robots and where the bottleneck is.
More about how the system works in “How we built RMS”.
Payback
CarGo 300 starts at about $14,500 depending on order volume. If the robot covers the trips previously made by one employee with a cart per shift (roughly $12,000–18,000 a year including taxes, depending on the region), it pays back in about a year. With two or three shifts, faster.
A real “storage → assembly line” route is described in the case study “CarGo 300 at an automotive plant”.
We will calculate it for your site
Send us route lengths, trips per hour and load type, and we will come back with the number of robots and payback.